Must progress in the First Floor Restrooms has occurred, and now it is time for the boring things: electric and plumbing. An electrical inspector will be coming on Tuesday so that the restrooms can go live and the plumber should get some things...[ abbreviated | read entire ]
As many of you saw today, the old walls are gone and new walls are going up already. The flooring is removed and now the work to build the restrooms has begun. A plumber and electrician should be coming this week to begin their portions of the...[ abbreviated | read entire ]
Well, it has arrived, the port-a-john. It's not exactly what we wanted, but we wanted to be able to accommodate any with disabilities among us or that come to visit, and the one we got is the only kind we could find. It will stay there until the...[ abbreviated | read entire ]
It looks as though demolition is nearing completion. On Tuesday, the wall to the hallway was knocked down, so they should be getting close to being done. The plumbing will be one of the last things to go, so that we don't have to close the 2nd...[ abbreviated | read entire ]
As many of you saw today, much progress has occurred this week. One of the main reasons we are renovating the first floor restrooms is that we don't have enough capacity. No without those restrooms, it is even worse -- BUT, there is hope. There...[ abbreviated | read entire ]
Demolition was going to begin on Monday, but we forgot about voting, which would have been disrupted, so it began today. It's amazing how much destruction can happen in one day! There is actually a hole cut in the wall between Liz's old office...[ abbreviated | read entire ]
Welcome to the new Renovations Blog! We will be using this to keep everyone up-to-date on the latest renovations news, so you know what is going on and what to expect. The Deacons have been working really hard to meet the deadline of May 1 to...[ abbreviated | read entire ]